Closure and reopening of stations zavírání a zprovozňování stanic zasažené povodní v srpnu 2002
Between 13th and 15th August Prague saw the biggest flood for more than 100 years. Apart from other parts of Prague, also big parts of the metro system were flooded.
The extent of the inundation can be seen on this map. Photos from flooded stations can be found here.
In total, 19 stations were flooded:
Line A: Malostranská, Staroměstská, Můstek, Muzeum
Line B: Smíchovské nádraží, Anděl, Karlovo náměstí, Národní třída, Můstek, Náměstí Republiky, Florenc, Křižíkova, Invalidovna, Palmovka, Českoravská, Vysočanská
Line C: Nádraží Holešovice, Vltavská, Florenc
Operations were continued only on these routes:
Line A: Náměstí Míru - Skalka
Line B: Nové Butovice - Zličín
Line C: Muzeum - Háje
Almost every day new schemes of operations were published, you can find them all here.
Closure of stations and routes on the critical days
Date
Line
routes (stations) out of service
From - To
12.8.2002
C
Nádraží Holešovice - Florenc 23:00 - 24:00
13.8.2002
C
Nádraží Holešovice - Florenc 0:00-24:00
B
Křižíkova 4:30-24:00
B
Invalidovna 11:20-24:00
A
Malostranská, Staroměstská 14:30-24:00
A
Dejvická - Náměstí Míru 22:00-24:00
B
Florenc - Smíchovské nádraží 22:00-24:00
14.8.2002
A
Dejvická - Muzeum 0:00-14:00
A
Dejvická - Náměstí Míru 14:00-24:00
B
Nové Butovice - Černý most 0:00-24:00
B
Zličín - Černý most 14:30-16:10
C
Nádraží Holešovice - Pražského povstání 0:00-9:00
C
Nádraží Holešovice - Muzeum 9:00-24:00
15.8.2002
A
Dejvická - Náměstí Míru 0:00-24:00
B
Nové Butovice - Černý most 0:00-22:00
B
Zličín - Černý most 22:00-24:00
C
Nádraží Holešovice - Muzeum 0:00-24:00
Reopening of metro stations and routes
Date
Line
route (station) out of service
Change valid from
16.8.2002
B
Zličín - Nové Butovice 14:00
B
Hloubětín - Černý Most 14:00
26.8.2002
B
Nové Butovice - Smíchovské nádraží beginning of operations
12.10.2002
C
Hlavní nádraží beginning of operations
19.10.2002
C
Florenc beginning of operations
26.10.2002
A
Muzeum beginning of operations
16.11.2002
C
Nádraží Holešovice beginning of operations
9.12.2002
B
Anděl a Karlovo náměstí beginning of operations
16.12.2002
B
Palmovka, Vysočanská, Kolbenova beginning of operations
21.12.2002
A
Dejvická, Hradčanská, Můstek beginning of operations
21.12.2002
C
Vltavská beginning of operations
16.1.2003
A
Staroměstská, Malostranská beginning of operations
31.1.2003
B
Českomoravská beginning of operations
17.2.2003
B
Můstek, Florenc beginning of operations
17.2.2003
C
Eskalátor - Florenc exit direction Těšnov beginning of operations
1.3.2003
B
Národní třída and Náměstí Republiky
beginning of operations
1.3.2003
B
opening second vestibul of station Vysočanská (Nádraží Vysočany)
beginning of operations
1.3.2003
A
opening second vestibul of station Můstek (under the lower part of Wenceslav sq.). beginning of operations
15.3.2003
B
opening second vestibul of station Karlovo náměstí (Palacky sq.). beginning of operations
22.3.2003
B
Křižíkova, Invalidovna beginning of operations
29.3.2003
B
opening second vestibul of station Anděl (Na Knížecí) beginning of operations
29.3.2003
B
opening second vestibul of station Náměstí Republiky (Masarykovo nádraží) beginning of operations
Assessment of the costs for the restoration of the complete metro operation: cca 6 995 000 000 Kč